Project participants are becoming more aware of the high costs and risks associated with
delay claims and their litigation. Among delays, weather delay has an important role in projects
performed in severe environmental conditions. This research is the extension of delay analysis
techniques by approving analysis of weather delays using fuzzy logic. At the presented technique,
first using a fuzzy logic model calculated the delay that occurred during the activity execution after
weather event then by the selected delay analysis method (Time impact analysis) and using the risk
of the contractor during the contract approval together with the effect of previous delay in changing
the duration of activities, analyzed weather delays in construction project. A local general
contractor and governmental firms involved in a highway construction project practiced by offering
their experienced and knowledge in delay analysis procedures to provide data for development and
testing of the model specified for rain events. The results indicated that the presented model is in
accordance with practical experiences in weather delay duration except in some circumstances that
can be divided into the separated parts. It also advances the use of fuzzy logic in delay analysis
procedures and becomes it more systematic special for weather delays.